Samsung SDS Gumi AI Data Center

Also known as Samsung SDS Gumi 60 MW

Operated by Samsung SDS at Samsung SDS Gumi Site .

Phase 1 seed dataset, compiled by hand. These rows were built from public operator, laboratory and vendor sources. A mechanical second-reader pass has since fetched every cited source: 1263 of 1345 systems have a readable citation that names them, and 56 are genuinely weakly sourced. Every claim carries its source and a confidence tier. Treat anything below verified as a lead, not a citation.

Measured performance

Rmax
-
Rpeak
-
Rmax ÷ Rpeak
-
Cores
-
Power
-
Per watt
- GF/W

Figures are as last publicly reported for the configuration described below, not a live measurement. Where a system was upgraded in place, the post-upgrade configuration is shown and the earlier one appears in the timeline.

What this machine is made of

One row per supplier relationship. “Supplier at build” is the company that shipped the part at the time; where that company has since been acquired, the parent it rolls up to today is shown beside it. That distinction is what makes ticker-level aggregation possible across a thirty-year dataset.

Role Part Supplier at build Quantity Confidence Source
Integrator -
Samsung SDS is building and will operate a 60 MW AI data center at Gumi on the former Samsung Electronics Gumi Plant 1 site; accelerator model and count not stated
Samsung SDS
- Reported samsungsds.com
Cooling -
Hybrid cooling: chilled water delivered directly to high-power GPU servers and air cooling for network and storage equipment
Samsung SDS
- Reported samsungsds.com

AI datacenter metrics

Figures beyond an accelerator count, each with who stated it. What can and cannot be compared across AI datacenters.

MetricValueAs ofBasisNoteSource
Facility power 60 MW 2026-01-12 Design target Samsung SDS states a 60 MW AI data center at Gumi, operations scheduled for March 2029; IT versus total not stated. samsungsds.com

The read

A 60 MW AI data center that Samsung SDS signed an MOU on 7 January 2026 (announced at CES 2026) with Gyeongsangbuk-do province and Gumi city to build on the former Samsung Electronics Gumi Plant 1 site, which SDS acquired in December 2024. Operations are scheduled to begin in March 2029. The design uses hybrid cooling, with chilled water delivered directly to high-power GPU servers and air cooling for network and storage gear. No accelerator model or count is stated. TechRadar confirms the land purchase and SDS's existing Gumi data center but not the 60 MW figure, so the tier is reported. It has never submitted an HPL result.

Timeline

Site & facility

Samsung SDS Gumi Site

Location
Gumi, South Korea
Cooling
Hybrid cooling: chilled water direct to GPU servers, air cooling for network and storage equipment
Commissioned
2029

Change history

Source check

We fetched this system's own citations and recorded whether each page actually mentions it. This is a corroboration signal, not a fact check, and it is published so you can see how well the sourcing holds up rather than take it on trust.

Cited sourceResultFound on the page
samsungsds.comnames system only-
techradar.comnames system only-

Checked 2026-10-13 by pnpm verify. Re-run it and the table changes with the web.